Budget requested for phase two of Phuket Town Flood Prevention project

Budget requested for phase two of Phuket Town Flood Prevention project

PHUKET: Authorities have requested an additional budget from the government to allow work to commence on the second phase of the Phuket Town Flood Prevention project.

constructionenvironmentweather
By Eakkapop Thongtub

Saturday 22 February 2020, 02:11PM


This follows a visit the Deputy Minister of Interior, Songsak Thongsri, paid to the project at Suan Luang (King’s Park) on Thursday (Feb 20) for an update on progress and to ensure everything is on track to be completed by the October deadline.

This inspection is to follow up on the progress of the project and an opportunity to meet relevant people, in order to make sure the project will be finished in time, and the budget was used reasonably,” commented Mr Songsak.

Also present at the inspection were Vice Governor Wongsakorn Nunchukan; Public Works and Town Planning and Country Planning Department (DPT) Phuket Office Chief Sommit Somboon; Department of Public Works and Town & Country Planning in Bangkok (DPT) inspector Suwapong Poonakpunt; Phuket City Deputy Mayor Thawon Jiraphattanasopon, and other relevant officers.

The project started on April 18, 2016 and is scheduled to be completed on Oct 21 this year. Currently, about 44% of Phase 1 is complete.

Deputy Mayor Thawon explained, “The government granted Phuket City Municipality a budget of B517.6 million to solve flooding issues and to improve the drainage system in Phuket Town.

On March 31, 2016, the Ministry of Interior contracted the construction company Auang Sea Heang Co Ltd to complete the works. There was a small detail change to the contract in 2018 but it is scheduled to be finished by Oct 21,” Mr Thawon confirmed.

Phase two

Planning for phase two of the project is now underway and Deputy Mayor Thawon confirmed a request for funds has been made.

We have now filed a request for additional budget for phase two which consists of eight sub-projects, he said”

He declined to reveal the phase two budget cost, stating only: “We hope the budget will be approved.”

DPT inspector Mr Suwapong explained that the second phase of the project includes two parts divided into 13 sub-projects as follows:

Part 1: Drainage system quality development project, including 10 sub-projects.

1. Weir building in Klong Bang Yai

2. Weir building in Klong Ruamjai

3. Drainage system building in Suan Luang

4. Drainage system building in Klong Lad

5. Drainage system building in Klong Saen Suk

6. Drainage system building in Klong Ruamjai

7. Drainage system building in the second part of Klong Ruamjai

8. Drainage system building near Amphoe Rd

9. Drainage system building in Klong Bang Yai

10. Drainage system building in Klong Thaklaeng

Part 2: Water pumping station building project, including three sub-projects.

1. Water pumping station building near Klong Bangyai

2. Water pumping station building near Klong Saensuk

3. Water pumping station building near Klong Ruamjai

Mr Suwapong explained that once the project was completed, people in Phuket Town will not experience flooding anymore.

Comment on this story

* Please login to comment. If you do not have an account please register below by simply entering a username, password and email address. You can still leave your comment below at the same time.

CAPTCHA

Be the first to comment.

Have a news tip-off? Click here

 

Phuket community
Living with COVID-19

It never ceases to amaze me that, a; people are allowed to use such arrant nonsense in what is obvio...(Read More)


Living with COVID-19

Fairly sensible, I take a lot more zinc than that. I also agree about only eating during 8 hours,...(Read More)


Fears raised for elephant welfare as Phuket camps fold

This is a complete failure by camp operators, to not have a contingency or back up. It is also a fa...(Read More)


Canadian children among Phuket COVID-19 infected, total confirmed cases hit 69

Thank you for this good reporting. Any way to please get more info on the original 23 or so re the...(Read More)


Fears raised for elephant welfare as Phuket camps fold

Another result of short-sightedness and greed. The first casualty is the elephant, which shouldn'...(Read More)


Fears raised for elephant welfare as Phuket camps fold

@Rorri. I agree ! Sadly this won't happen and in the near future it will all be business as u...(Read More)


Fears raised for elephant welfare as Phuket camps fold

Close all this elephant,tiger ,monkey +++ place’s forever. And all this owners have made millions ...(Read More)


Fears raised for elephant welfare as Phuket camps fold

"Dire fears for the welfare of thousands of elephants throughout the country have been raised w...(Read More)


Tiger believed to have killed man in national park

I thought national parks were close, anyway, what fool goes out , at night, looking for what is thou...(Read More)


Phuket hotels look to close during lockdown

We're Italian tourists and beacause our Country has been the first to be banned right now has no...(Read More)