Phuket Governor rails as project to bury Patong cables underground stalls

PHUKET: Phuket Governor Norraphat Plodthong this morning ordered Provincial Electricity Authority (PEA) officials to get moving on having power cables in Patong installed underground after the project silently stalled in May this year.

tourismpatongconstruction
By Tanyaluk Sakoot

Tuesday 12 December 2017, 12:44PM


Workers cut cables in Bangkok where the project to clear overhead wires is making progress. In Patong, however, no progress has been made in the past two years. Photo: Bangkok MEA

Workers cut cables in Bangkok where the project to clear overhead wires is making progress. In Patong, however, no progress has been made in the past two years. Photo: Bangkok MEA

“The project to install the power cables underground in Patong has taken too long,” Governor Norraphat said at an early morning meeting, which got underway at the Governor’s House at 7:30am.

“I want progress on this project. You have the budget to build it… You know I have asked about this many times, and so have many others,” he added.

Present to respond in person to Governor Norraphat’s call for action was Vachira Phitaktansakul, Governor of Construction and Project Management at the national PEA headquarters in Bangkok.

Mr Vachira’s presence follows his predecessor, Panya Laochu, announcing more than two years ago, “A 33KV power-supply cable will be installed along three kilometres of the beach road, from the Klong Pak Bang bridge (at the southern end of Thaweewong Rd) to the intersection with Ruamjai Rd.

“The contract has been signed and comes into effect in April 2016, allowing 18 months for the contractor to complete the project. We believe construction will begin in July 2016,” Mr Panya told the press after a meeting at the Phuket Graceland Resort & Spa, in Patong, on Dec 16, 2015. (See story here.)

However, Mr Vachira this morning explained, “The B224-million contract to install the cables underground in Patong has stalled because the contractor rejected the ‘technical plan’ for the project in May 2017.

“They cannot work on this plan, as the technical plan no longer caters to present demands,” Mr Vachira added.

“We have to draw up new plans for this project, and we will hold a meeting to clarify with communications companies this month,” he said, alluding to the original intent of having only the power cables buried now being expanded to include having telephone and internet cables installed underground with them.

“We will then draft a new contract that must be approved before opening the contract to bidding, which we expect will be in April 2018.

“But we will push for the construction to start that same month. The contracted construction period will be the same – 540 days” Mr Vachira added.

On hearing the update, Governor Norraphat made plain his concerns that the public remain uninformed of what is happening with the project.

“Everything must be published for people to see. You have to tell the people what are you doing. So go and post signs to let them know,” he said.

 

 

Comment on this story

* Please login to comment. If you do not have an account please register below by simply entering a username, password and email address. You can still leave your comment below at the same time.

Comments Here:
Comments Left:
# Characters
Username:
Password:
E-mail:
Security:

Kurt | 12 December 2017 - 13:48:08

So the original 'intend' was only about the power cables, excluding the telephone and internet cables.
Meaning: After the enormous power cable work mess of 540 days there would have been still hanging/dangling cables.
Strange project intention.

By the way, was there no need to ask the tuk tuk and taxi 'administration' permission for this project seen the limitation of their pa...

Have a news tip-off? Click here

 

Phuket community
Government clamps down on surging illegal Thai migration

140,000 illegal thai workers in Korea. Wow. Obviously thai Immigration should check better on depart...(Read More)


Phuket Opinion: Recalibrating the retirement visa

Talking about thai NIDAL Polls: In BP of 19 May an article that according a NIDAL poll 31.25% of th...(Read More)


Phuket Opinion: Recalibrating the retirement visa

Was there any NIDAL Poll, proving that retirees, with their 800,000 Baht deposit are more hospitalis...(Read More)


Phuket Opinion: Recalibrating the retirement visa

can he explain why retirees need to keep 800k in the bank? Probably has no idea about that,not his m...(Read More)


Mains water supply to be shut off near airport

Well done, PWA. You choose the most quiet hours at Phuket International Airport to shut of her water...(Read More)


Phuket Opinion: Recalibrating the retirement visa

My retirement visa is yearly from 15 September till 15 September. My International health insurance...(Read More)


Senior monks jailed for fraud

See the look on his face, no sign of feeling guilt or sorry. This was not a thai buddhist monk, but...(Read More)


Phuket Opinion: Recalibrating the retirement visa

They know full well it's the short stay tourists that are not paying their bills. I'm sure m...(Read More)


Phuket Opinion: Recalibrating the retirement visa

Good PN Opinion piece. This 'action' is very thai. ."First do something, think about d...(Read More)


Cabinet approves mandatory health insurance for long-stay visas

"No need to panic!" No, but on that web site are thai insurances only, just covering Thai...(Read More)